Etude d'Intégration Goniomètre JP.CORSO le 4/11/2011

3D Catia : ST0378587_01 (C4L7) & ST0378575_01 (C4R7)

Requests :

  • Check the feasibility of integration for one or two Goniometers on Beam 1 (ext) in the LSS7, at the following DCUM : 19946, 20010, 20044

  • Provide the volume available for those devices.

First acceptance is to take the slot as a collimator, i.e. 1480mm long.

Following 2 drawings show in yellow the areas for the DCUM requested. In Green were added areas proposed by Integration, considering that those locations have less environment devices to avoid (cables trays, pipes, ventilation duct)

DCUM proposed (start of area) are mentioned on the TOP Views

C4L7 - DCUM 19946
C4R7 - DCUM 20010 & 20044
Global View R76-UJ76